Summary
A practical overview of the process for developing data centres in Ontario, from site selection and land-use planning through Site Plan Approval, engineering, building permits, construction and commissioning. The article highlights key considerations including power availability, water and cooling, site servicing, municipal approvals, environmental requirements and the importance of coordinating planning and engineering early in the project.
An integrated roadmap from site feasibility to commissioning
Data centres are not simply large buildings filled with servers. They are power-intensive, MEP-intensive, mission-critical infrastructure projects whose viability depends on aligning land-use policy, utility capacity, municipal servicing, environmental permissions, resilient building systems, critical-equipment procurement and commissioning—often years before the first racks are energized. Canada’s 2026 Responsible Data Centre Development Principles reinforce that projects should protect electricity ratepayers, minimize water and environmental impacts, disclose local impacts and create durable community benefits; they also recognize that decisions remain fundamentally local and are shaped by provincial, municipal and Indigenous processes. For owners, developers and investors, the most important lesson is that land, approvals, power and procurement cannot be treated as sequential silos. Hydro One describes a transmission connection as a seven-phase process—application, impact assessment, estimate, approval, design/build and commissioning—and says an average connection can take two to five years, with land, approvals and project complexity extending it further. Ontario’s own 2026 review of Site Plan Control reported a 60-day legislated decision window but an average municipal review duration of 23 months, with non-residential projects taking longer in the study reviewed by the Province.
RISKS
Power is a site-selection question
A parcel is not “data-centre ready” merely because a transmission line or substation is nearby. Capacity, connection configuration, upgrades, approvals, cost allocation and energization dates must be confirmed.


RISKS
Site Plan Approval Takes Time
Municipal approvals, utility studies, environmental permissions, redesign, equipment procurement and commissioning have separate clocks that may overlap, conflict or extend the overall programme. Schedule your project with at least 2 years for the approvals process.
RISKS
Scale changes the project
A regional enterprise facility may fit existing municipal and electrical infrastructure. A hyperscale campus can trigger transmission upgrades, substations, generator and fuel yards, water analysis and phased servicing.


1. Sale determines site and infrastructure requirements
“Data centre” covers a wide range of facilities. A regional or enterprise facility serving a defined organization or market may occupy one building and connect through an existing local distribution system. A large colocation, cloud or hyperscale campus may require transmission-level service, dedicated transformation, substantial standby generation, multiple fibre routes, larger heat-rejection systems and land reserved for future phases. Uptime Institute’s design framework treats prime and contingency power, network routes, cooling, cable management, safety, structural and site elements as an integrated reliability problem—not independent specifications.
| Constraint | Regional or enterprise facility | Large or hyperscale facility |
|---|---|---|
| Electrical power | May be serviceable through an LDC, subject to confirmed capacity, voltage, reliability and upgrade requirements. | May require transmission connection, new or expanded substations, network reinforcement, staged energization and formal IESO/Hydro One studies. Ontario is currently developing additional technical requirements for large computational loads. |
| Redundancy | Redundant utility, UPS and generator arrangements are selected against the owner’s uptime and business-continuity objectives. | Redundancy creates larger electrical rooms, switchyards, busways, batteries, generator compounds and maintenance clearances. Redundancy should be performance-based rather than assumed from a generic “Tier” label. |
| Backup generation | Fewer units and smaller on-site fuel requirements may be feasible. | More units mean greater land take, exhaust, acoustic attenuation, fuel delivery/storage, fire-protection and spill-containment implications. Air, noise or vibration approvals may apply depending on equipment and operating mode. |
| Water and cooling | Air-cooled, refrigerant, evaporative or liquid-assisted strategies may work depending on load and climate. | Cooling selection can materially change potable-water demand, water-taking permissions, wastewater and heat-rejection infrastructure. Water use is location- and technology-specific; water-cooled systems may be efficient in water-rich areas, while air-cooled approaches may suit water-stressed sites. |
| Noise | Equipment can sometimes be enclosed or screened within a compact site. | Multiple generators, cooling towers, dry coolers, transformers and ventilation systems create cumulative sound sources. Receptors, emergency testing, tonal characteristics and phasing should be modelled early. |
| Site servicing | Existing roads, water, sanitary and storm services may have adequate reserve capacity. | Rural or edge-of-settlement sites can require road improvements, water storage, fire flow, private servicing, industrial stormwater permissions and major utility corridors. Industrial cooling water and stormwater are regulated as sewage works where applicable. |
| Land and phasing | Compact development may prioritize reuse or infill. | Campus planning requires setbacks, security zones, stormwater facilities, cooling and generator yards, substations, future data halls and construction access that does not disrupt live operations. |
Power availability is often decisive. A nearby line does not establish deliverable capacity. The utility must assess system impacts, customer impacts, protection, easements, approvals, cost responsibility and the facilities required to energize the load. Hydro One identifies 12 months or more for customer-impact assessment, eight months or more for connection estimates and one to two years for design/build within its larger connection process.
2. Ontario’s approvals framework
Zoning, variance and Site Plan Control
The first planning question is whether the proposed use is permitted by the Official Plan and zoning by-law. If it is not, an Official Plan or zoning amendment may be necessary; limited dimensional relief may be addressed through a minor variance where the statutory tests can be met. These discretionary processes are distinct from Site Plan Control and may involve notice, public input, council or committee decisions and appeal risk. Under section 41 of Ontario’s Planning Act—and section 114 of the City of Toronto Act in Toronto—Site Plan Control is primarily an administrative and technical review of building placement, access, loading, lighting, drainage and other site-function matters before building construction. It is not intended to reopen the principle of a use already permitted by zoning. The legislation does not itself require a public meeting for a Site Plan application, although community concerns may arise through related zoning, environmental or municipal processes. A municipality may circulate the submission to engineering, transportation, fire, operations, utilities, conservation authorities, railways and other agencies. Comments can lead to revised drawings, additional material, recirculation and repeated resubmission. Approval may include conditions, a registered Site Plan Agreement, easements, road works and financial securities; final clearance can remain outstanding after technical acceptance while agreements and conditions are completed.
Building permit and applicable law
Ontario’s 2024 Building Code came into force on January 1, 2025, and became mandatory for new permit applications after the transition period. A permit cannot be issued where the work would contravene the Building Code or another “applicable law,” which can include zoning, Site Plan approval and certain environmental or conservation permissions. The Building Code assigns class-based permit-review periods once an application is complete and fees are paid; the regulatory table provides a 20-business-day period for large buildings and 30 days for certain complex or post-disaster buildings. That is not an end-to-end development schedule: incomplete information, applicable-law clearances, permit comments, design revisions and owner response time sit outside a simple statutory review number.
Conservation and environmental permissions
Conservation authority involvement is site-specific and may arise near regulated watercourses, wetlands, shorelines, erosion hazards or flood-prone lands. Other potential approvals include an Environmental Compliance Approval or EASR registration for air, noise, vibration or sewage works; a Permit to Take Water for most takings above 50,000 litres per day from the environment; source-water requirements; and industrial stormwater or wastewater permissions. Ontario identifies a one-year service standard for most ECA applications, while noting that application quality, information requests and Indigenous consultation may change actual review time. PTTW applications undergo completeness screening, technical review and, where required, at least a 30-day Environmental Registry consultation, with water availability, ecosystems, other users and source protection among the decision factors.
What generalizes across Canada?
Every province has its own planning legislation, building-code adoption, environmental permissions, utility regulators and conservation or watershed regimes. What generalizes is the need to demonstrate permitted land use, obtain local development and building approvals, secure electrical and telecommunications capacity, address environmental effects and satisfy provincial building/fire requirements. Canada’s national principles intentionally complement—not replace—provincial, territorial, municipal and Indigenous processes.
3. Why “two years or more” is a credible project risk
Two years should not be presented as a universal statutory benchmark. It is a scenario that can arise when independent processes accumulate:
- land acquisition and title investigation;
- utility feasibility, system-impact and customer-impact studies;
- zoning or variance work, where required;
- archaeological, environmental, geotechnical and servicing investigations;
- Site Plan circulation and resubmissions;
- environmental permissions;
- permit design and building-permit comments;
- long-lead equipment procurement;
- construction, testing and occupancy readiness.
Ontario’s 2026 Site Plan review found that incomplete applications, delayed responses, department/agency coordination and multiple resubmission cycles contribute to durations far beyond the 60-day non-decision appeal point. Hydro One separately advises that transmission connections average two to five years and that approvals, land issues and complexity can extend them significantly. Equipment adds another clock. Current North American contractor procurement data reports extended lead times for medium-voltage switchgear, substation transformers, large generators, UPS systems and automatic transfer switches, while cautioning that actual dates depend on manufacturer, configuration and quantity. These figures should be replaced by project-specific Canadian OEM and utility quotations before underwriting a schedule. The correct planning message is therefore:
A two-year-or-longer development period is a material risk where land-use approvals, utility connection, environmental permissions, technical redesign and long-lead procurement interact. It is not the statutory duration of Site Plan Approval or a guaranteed outcome for every project.
4. Feasibility and land-use planning
A disciplined feasibility phase should establish the usable development area, target building and campus capacity, initial capital plan and critical-path constraints before major design expenditure or unconditional land acquisition.
Recommended feasibility scope
- Review Official Plan designation, zoning, Site Plan applicability, adjacent sensitive uses and required setbacks.
- Prepare a preliminary site plan showing the building, future phases, parking, secure access, fire routes, loading, substations, generator/cooling compounds, fuel delivery, stormwater and utility corridors.
- Request municipal pre-consultation and utility capacity discussions.
- Engage a surveyor to review boundaries, easements, title constraints, rights-of-way and existing Site Plan agreements.
- Prepare initial data-hall, office, operations and electrical/mechanical layouts.
- Establish initial redundancy, cooling and commissioning objectives.
- Develop a Class-level capital estimate with allowances for utility upgrades, studies, securities and escalation.
- Screen relevant municipal, provincial or federal incentive programmes without assuming eligibility.
Toronto’s guidance illustrates the value of pre-consultation: it identifies project-specific studies and complete-application requirements before submission. However, municipal feedback is preliminary, and neither staff discussion nor political interest guarantees approval. For data centres, the site-selection matrix should also score firm power capacity and energization date, proximity to viable connection points, diverse fibre routes, municipal fire flow, cooling-water strategy, wastewater/stormwater capacity, flood and climate resilience, equipment noise receptors, access, security, geotechnical conditions and room for phased expansion.
5. Site design and supporting studies
Not every application requires every study. Pre-consultation should establish the municipality’s formal submission list, while the project team identifies additional studies needed for investment and design decisions. Common investigations for a large greenfield industrial/data-centre site may include:
- legal, topographic and utility surveys;
- geotechnical investigation;
- environmental site assessment;
- archaeological assessment where triggered;
- servicing, grading, drainage and stormwater reports;
- hydrogeological investigation where wells, groundwater, infiltration, dewatering or private sewage are relevant;
- traffic and access assessment;
- water-demand and fire-flow analysis;
- electrical load, connection and energy studies;
- natural-heritage or environmental-impact analysis where triggered;
- acoustic study for cooling, transformers and generators;
- air-emissions analysis where generator or combustion approvals require it;
- source-water and water-taking work where applicable.
Ontario requires environmental permissions for many industrial sewage, process-water and stormwater works and recognizes cooling water as wastewater. Air/noise ECAs or EASR requirements are activity-specific, so generator and cooling selections should be screened before the site plan becomes fixed. Energy review should consider envelope performance, solar heat gain, heat-recovery opportunities, cooling architecture, electrical losses and on-site solar or other generation. On-site generation or microgrids may support resilience or constrained-grid strategies, but they introduce electrical-safety, fuel, emissions, operating and utility-interface requirements rather than eliminating approvals.
6. Coordinated Site Plan submission
A strong submission should reconcile planning, civil, utility, architectural, landscape, fire-access and environmental information before circulation. Each resubmission should include coordinated drawings and a clear comment-response matrix. Toronto’s process explicitly contemplates circulation to departments and external agencies, revision, recirculation and repeated resubmissions until the application is finalized. Local knowledge matters because development decisions occur within municipal policy, infrastructure capacity, technical standards and community priorities. This is the professional sense in which land development has a political and stakeholder dimension: the project team must understand how council priorities, neighbouring uses, service constraints and public concerns affect risk. Local relationships improve communication and issue resolution, but cannot properly assure an outcome or replace statutory and technical requirements.
7. Multidisciplinary building design
IN Engineering + Planning’s preferred progression can be structured as approximately 33% concept, 66% design development and 99% detailed/permit-ready design, recognizing that terminology varies by client and delivery model. Enterprise material already describes gated design stages, interdisciplinary coordination, constructability, permitting, tendering and construction support.
Discipline priorities
- Architectural/building design: data-hall layout, operational areas, security zoning, access control, envelope, egress and maintainability.
- Structural: equipment, battery, generator, busway and roof loads; vibration; foundations; equipment plinths; penetrations; future expansion.
- Civil: access, fire routes, heavy-equipment delivery, grading, utilities, stormwater, fuel areas and phased servicing.
- Mechanical: cooling topology, heat rejection, water use, filtration, controls, redundancy, drainage, leak detection and maintainability.
- Electrical: utility interface, transformers, switchgear, selective coordination, UPS/batteries, generators, grounding, lightning protection, arc-flash considerations and monitoring.
- Plumbing/fire protection: domestic and process water, sanitary and storm systems, floor drainage, fire-water storage where needed, sprinkler/standpipe systems and fuel-system interfaces.
Occupancy classification, fire separations and ancillary-office treatment must be determined for the actual building configuration; there is no single universal “data-centre occupancy.” Ontario requires professional design and general review where triggered, while Uptime certification addresses infrastructure reliability and does not replace local code compliance.
Steel, prefabrication and modular delivery
Pre-engineered or conventional structural steel with concrete foundations and slabs can be economical where large spans, repetitive bays, equipment loads and future expansion align with the system. Prefabricated power, cooling or data-hall modules can improve repeatability and move work off-site, but transportation limits, module interfaces, fire/code requirements, equipment access and utility coordination remain project-specific. IN Engineering + Planning’s enterprise proposals position the firm around multidisciplinary building design, constructability, procurement coordination and modern/off-site delivery rather than a blanket commitment to one structural system. VDC/BIM is particularly valuable because architectural, structural, mechanical, electrical, plumbing and fire-protection systems compete for dense service zones. Federated models can identify hard clashes, clearance conflicts, equipment-access issues and penetrations before installation; issue tracking must then assign, revise and verify each resolution rather than simply generate a clash report.
8. Permit, procurement and pre-construction
The building-permit package should be coordinated, sealed and sufficiently complete to demonstrate Building Code and applicable-law compliance. Permit comments should be tracked through a consolidated response, with changes reflected across all affected disciplines. Material design changes after permit issuance require notification and authorization by the Chief Building Official. Tendering and early procurement may overlap permit review where the contractual strategy and owner’s risk tolerance support it. Transformers, switchgear, generators, UPS/battery systems, automatic transfer equipment and cooling plant should have preliminary specifications and substitution rules early enough to reserve realistic supply positions. Procurement decisions made before final approvals must clearly allocate redesign, cancellation, storage and regulatory risk. Pre-construction should include shop-drawing protocols, approved substitutes, model coordination, constructability review, equipment access, temporary works, schedule and budget controls, commissioning requirements and site-mobilization conditions. Clearing, excavation or foundation work should not begin until the necessary permits, environmental controls and conditional-permit terms—if any—are in place.
9. Construction, commissioning and closeout
The contractor remains responsible for construction methods, sequencing, quality control and compliance with the permit. Consultants respond to RFIs, issue clarifications or supplemental instructions, review submittals within their scope, evaluate design changes and undertake required general review. PEO describes general review as periodic observation on a rational-sampling basis to form an opinion on general conformity—not continuous inspection, contractor quality assurance or approval of construction methodology. Municipal building officials conduct statutory inspections, while professional general review reports document observed work, deficiencies and relevant testing. Change control is especially important where a substitution affects electrical coordination, generator/cooling loads, structural support, acoustics, emissions, controls or commissioning sequences. Commissioning should progress from component and factory testing through installation verification, start-up, controls testing, balancing, electrical protection, UPS/battery testing, generator and transfer sequences, cooling failure scenarios, life-safety testing and integrated systems testing. Uptime’s standards distinguish design-document review from constructed-facility validation, reinforcing that a compliant design alone does not prove installed performance.420233115c.png Closeout should include deficiency correction, occupancy readiness, final general-review reports, testing records, approved changes, as-built drawings, O&M manuals, training, warranty registers and post-occupancy support. Under Ontario’s legislation, occupancy depends on required notices, inspections, orders and applicable occupancy conditions—not simply contractual handover.
10. IN Engineering + Planning’s integrated role
IN Engineering + Planning is an integrated team for land-use planning, civil and structural engineering, building design, municipal coordination, project management, permitting, procurement assistance, construction administration and commissioning/closeout support.
If you require consultants for your industrial, manufacturing or data centre project, contact us at engineering@ineng.ca.
Practical risk-reduction priorities
- Make power a land-acquisition condition, not a post-closing design task.
- Meet the municipality, LDC/Hydro One and fibre providers early.
- Test title, environmental, geotechnical, water, stormwater and acoustic constraints before fixing the footprint.
- Reserve land and servicing for phased expansion.
- Advance planning, civil, building and utility design concurrently.
- Define redundancy and commissioning objectives before equipment selection.
- Carry quantified contingencies for approvals, utility upgrades, securities and procurement.
- Prequalify long-lead equipment and acceptable alternates early.
- Use VDC to coordinate installation, access, penetrations and maintainability.
- Retain local multidisciplinary planning and engineering expertise that can follow the project from feasibility through warranties.
The central project-planning principle is straightforward: a data-centre site is viable only when land use, power, water, servicing, environmental permissions, building systems, procurement and community context work together. An integrated team allows those risks to be identified while options are still open—rather than after land has been acquired, approvals submitted or critical equipment ordered.